May 26, 2016 — Kentucky: Blasting schedule for week of May 30, 2016: Site blasting is scheduled to occur near the tunnel’s north portal during the week of May 16. These blasts do NOT require traffic stops.
The dates and approximate times (within 20 minutes) will be:
• Tuesday, May 31, at about 12 p.m. noon and again at about 4 p.m.
• Wednesday, June 1, at about 12 p.m. noon and again at about 4 p.m.
• Thursday, June 2, at about 12 p.m. noon and again at about 4 p.m.
• Friday, June 3, at about 12 p.m. noon and again at about 4 p.m.
NOTE: A message will be posted on the project website at www.kyinbridges.com Thursday of each week regarding the anticipated blasting schedule for the following week.
In the event of unfavorable weather or other unforeseen activities, this schedule may change. When changes do occur, they will be posted on www.kyinbridges.com, on Twitter @eastendcrossing and on Facebook at http://ift.tt/1cA8FvY.
via East End Crossing http://ift.tt/1qMhYHe
No comments:
Post a Comment