Change in Blasting Schedule for Week of Sept. 16

The blasting schedule for the remainder of this week near the intersection of U.S. 42 and KY 841 has been altered. The dates and approximate times will be: Tuesday, September 17, at about noon and again at about 2:30 p.m. Wednesday, September 18, at about noon and again at about 2:30 p.m. Thursday, September 19, […]



via East End Crossing http://eastendcrossing.com/2013/09/change-in-blasting-schedule-for-week-of-september-16/ http://ifttt.com/images/no_image_card.png