Mowing will continue the week of April 30, 2018 along KY 841 and SR 265. Motorists are encouraged to move over to give equipment that is next to the road, plenty of room for safety.
via East End Crossing https://ift.tt/2HD8wQ3
Mowing will continue the week of April 30, 2018 along KY 841 and SR 265. Motorists are encouraged to move over to give equipment that is next to the road, plenty of room for safety.
Mowing will continue the week of April 23, 2018 along KY 841 and SR 265. Motorists are encouraged to move over to give equipment that is next to the road, plenty of room for safety.
The week of April 23rd, crews will be performing inspections of the Lewis and Clark Bridge from 8:00 am to 4:00 pm daily. Work will be completed by Friday afternoon on April 27th. Motorists can expect right lane closures in both directions on the bridge during these inspections. Drivers are reminded to slow down in work zones and stay alert for everyone’s safety.
Weather and ground conditions permitting, mowing crews will be out along SR 265 in Indiana and KY 841 in Kentucky this week mowing and weed eating. Please move over and give workers and equipment plenty of room for safety during these operations. Work will begin on April 16th and will be performed between 8 am and 5 pm daily, weather permitting, until operations are complete.
Crews will be sweeping the roadway on SR 265 and KY 841 in both directions in advance of shoulder sweeping on Thursday April 12th. Work will take place between 11 am and 3 pm. Work will be a moving operation to sweep dirt and debris to the shoulder to be swept up in a shoulder sweeping operation scheduled for the night of April 12th. Motorists are encouraged to slow down and give equipment and workers plenty of room for safety.
Starting at 7 pm on Thursday April 12th, crews will be sweeping the shoulders of SR 265 and KY 841. Work will be performed on the inside and outside shoulders of the road to pick up dirt and debris. Work will be completed by 6 am on Friday April 13th.
Crews will be cleaning bridges on the Lewis and Clark bridge starting April 10th. Work will take place between 11 am and 3 pm on Tuesday, Wednesday and Thursday. Work will cover all lanes in both directions but only one lane will be closed at a time. Motorists are reminded to slow down in work zones for everyone’s safety. Please give work crews plenty of room to work safely.
Starting Monday April 9th crews will begin tree replacement along SR 265 in Indiana. Lane closures are not anticipated but crew will be working next to the road and entering and exiting along the road for access to the work areas. Motorists are asked to slow down and watch for workers when in the area.
Starting Thursday April 5th, 2018, WVB will have a right lane closure eastbound at mile marker 10.2 on SR 265, to perform sign maintenance. The work will take place between 11 am and 3 pm on Thursday April 5th and or April 6th depending on weather and conditions. Crews and equipment will be present on the roadway and motorists are reminded to drive with care in the area.